Service Manager - Projects

Overview

The Service Manager can be used to manage projects. A project can be created for any task or process and ensures that the right steps are taken.

Projects support three indented levels as follows:

  • Milestones (grey): These are the project phases or major deliverables.
    • Task Groups (blue): These represent key activities or work packages.
      • Tasks (green): The individual tasks or actions.

Top Row Buttons Explained

Info

When a Task (Transaction) is created from a Project, the Project Task is checked to ensure the Resource is not blank and the Status is not in a Complete or Cancelled group.

Button Description
OutputOptions to print, email or preview templates (e.g. Project Plan or Project Progress).
EmailOptions to email internal or all subscribers.
NewCreates a service ticket.
EditLets you edit the ticket.
DeleteDeletes the ticket.
SaveSaves any changes.
ActionsSee Service Manager - Edit Views for details. The following functions apply to Projects and Components:
  • Create Transaction:
    • Quotation: Transaction items are created from the root level as follows:
      • Project Milestone Items are added to the Quotation as Items and include the Description and Note.
      • Qty = The number of hours.
      • Unit Price = Hourly Rate of the resource (Setup Service Manager > Project Resources (tab)).
  • Create Progress Invoice from Components > Customer Invoice: This function generates an invoice for the difference between the percentage complete and the percentage invoiced as follows:
    • Components are added to the invoice as items.
    • Qty = The percentage of the component that is completed.
    • Completion % = Percentage complete less the percentage invoiced so far.
    • Fixed Price = Total value of the project multiplied by the percentage completion as calculated above.
Start / StopStarts or Stops timekeeping.
Menu
  • Refresh: Updates the ticket with any changes.
  • View/Edit Subscribers: Edits the email recipients.
  • View Changelog: Displays a list of changes made to the ticket.
  • Open Timekeeping: Opens the timekeeping module.
  • Export Transactions
    • Export Grid
    • Email Excel
  • Layout & Grids

Project (tab)

Buttons Explained

Info

These are the buttons on the Project tab.

Button Description
ViewLists the tasks.
Actions
  • Batch Update: Changes all the selected entries when Update (button) is clicked and the updates are confirmed.
    • Status: Changes the status for the selected entry or entries and Project Template.
    • Tags: Adds or Removes the selected tags.
    • Resource: Allocates the task to the select resources.
    • Start: Sets the start date for the selected entries to the one selected from the calendar.
    • End: Sets the end date for the selected entries to the one selected from the calendar.
    • Days: Changes the entries' durations to the number of days entered in the adjacent block.
    • Est Hrs: Sets the estimated hours to the number entered in the adjacent block.
    • Billing: Sets the billing options to the one selected from the dropdown list. The options are: None, Fixed, Variable or Out of Scope.
    • Required Date: Sets the required date for the selected entries to the one selected from the calendar.
    • Move Dates by Days: Moves the Required, End or Start Days (as selected from the dropdown list) by the number of days entered in the adjacent block.
  • Schedule: Shows the Scheduling Fields and the Schedule button (see below).
  • Update Status from Template/s: Updates the Status options from the templates. (Changes to templates are not automatically applied to existing tickets.).
  • Delete: Deletes the selected entries.
AddProvides a dropdown list of templates for one to be added.
EditLets you edit the project.
ScheduleAppears when you select Actions > Schedule. Works in conjunction with the Scheduling Fields (see below) and provides the following options:
  • ASAP (From Project Start Date): Sets the start date to be as soon as possible. Does not affect dates that are fixed. The End date is automatically calculated. Works from the Start date and schedules the selected level based on one of these selections:
    • Every day
    • Exclude Sundays
    • Exclude Weekends
  • ALAP (From Project End Date): Sets the start date to be as late as possible. Does not affect dates that are fixed. The Start Date is automatically calculated. Works from the End Date and schedules the selected level based on one of these selections:
    • Every day
    • Exclude Sundays
    • Exclude Weekends
  • Set Start-to-Finish (SF) Predecessor: Creates all the predecessors based on the hierarchy.
  • Clear Predecessor: Clears any predecessors.
  • Set Audit Dates to Start Dates: Sets the audit dates (original planned dates) to match the start dates.
  • Change the Scheduling Level: Sets a different scheduling level.
Show Notes (Icon)Toggles displaying or hiding notes.
+ -Collapses or expands the tree view.

Scheduling Fields:

Info

The scheduling fields and the Schedule button are hidden until you select Actions > Schedule. To hide them again, click the X (Close) icon.

Button Description
StartSets the start date for the schedule, that is, the date on which the project will start or restart.
EndSets the end date for the schedule which should be the due date for the project.
LevelSchedules at the selected level (None, Tasks, Groups, Milestones)
Warning

Scheduling is set by days.

  • When a template is added to a project, the days on the levels that are not used for scheduling are cleared.
  • The Level can be updated by clicking Scheduling (button) > Change the Scheduling Level. A confirmation message displays that the days missing from the new Level are cleared (e.g. if tasks were scheduled, and the level is changed to Groups, the days next to tasks are cleared).

Filters Explained

Filter Description
ShowA dropdown list of milestones for you to select one or all.
Milestones, Groups and Tasks
  • Checkboxes. Check one or two levels to show only those levels.
  • If none are checked, all levels appear.
  • Milestones and Tasks cannot both be checked: checking one unchecks the other.
HrsCheckbox. If checked, the hours and variances appear.
Status Checkboxes
  • Only shows entries with the selected statuses.
  • If none of the boxes are checked, all the entries appear.
  • Hold your mouse over the checkboxes to see the name of the respective statuses.
  • The filter works on the fixed Status Groups and not the statuses created for the Project Template.

Fields Explained

Info

The level indicator is colour-coded as follows:

  • Grey: Milestones
  • Blue: Groups
  • Green: Tasks

Tasks can be rearranged by drag and drop.

Fields marked in blue (✎) can be edited.

Field Description
Field Chooser (*)Add or remove columns.
IDThe system-generated number for the entry.
ComponentThe system-generated number for the component.
Parent IDThe system-generated number for the parent (e.g. Milestone or Group).
Order IDThe system-generated number that depicts the order of the tasks.
TrackerThe system-generated number for the Tracker.
DescriptionThe description of the tasks.
PreviewDisplays a preview of any notes.
MilestoneThe name of the milestone. Blank if milestones are not used.
TagsThe tags that were selected for the task.
GroupThe name of the group. Blank if groups are not used.
BillingThe billing option for the group.
Work Process (Lookup)The selected Work Process / Select a Work Process. Work Processes is a fixed module that can be added to any Menu (e.g. Main Menu > Office > Processes).
Work ProcessDescription and hyperlink to the Work Process Documentation as filled in on the Work Process.
QualifiedLists the Staff who are qualified to perform the task (from Work Processes)
ResourceThe resource the task is assigned to.
Predecessor
  • The task or tasks that first must be completed before this task can start.
  • Predecessors can be applied at the same level in the same group only.
  • They are cleared when tasks are rearranged, and the predecessor ends up below the applicable task or if the task's dates are fixed.
RequiredThe date on which the customer wants the project to be complete.
StartThe start date of the task.
DueThe date on which production should complete the task.
Audit
  • This field contains the first Start Date of an entry and measures the days that the Start Date is Moved (d) from the original planned Date (hidden by default).
  • Audit dates can be reset to match the Start Dates from Schedule (button).
DaysThe number of days that the task should take.
NoteAny notes added to the task.
Est HrsThe estimate number of hours the task will take.
Moved (d)The number of days by which the dates were moved up.
Act HrsThe actual hours the task has taken. Only displayed if the Hrs checkbox is checked.
Var HrsThe difference between the estimated and actual hours (variance).
StatusThe status of the task.
CreatedThe date on which the task was created.
UpdatedThe date on which the task was last updated.
Created byThe user who created the tasks.
Updated byThe user who last updated the tasks.
ClockDisplays a clock if timekeeping is active (started) for the task.
Menu (...)A submenu that can also be accessed by right-clicking an entry with the following options:
  • Add Sub-item (Ctrl + Enter).
  • Insert Item Above (Ctrl + Up).
  • Insert Item Below (Ctrl + Down).
  • Duplicate (Shift + Alt + Down).
  • Move Up (Alt + Up).
  • Move Down (Alt + Down).
  • Tasks > Create New Task.
  • Add/Remove Tags.
  • View/Edit Task.
  • View/Edit Note.
  • Delete
  • Open Timekeeping
    • Note: This menu is only active in edit mode.

Components (tab)

Info

Components can be added directly to the Project or imported from the Items on a transaction that is linked to the Project and linked to the Transaction Setting > Transaction used for Quotations.

Buttons Explained

Button Description
Add ComponentAdds a line for a component to be entered.
Import ComponentsOpens a dropdown list of available components to import them. Can only be used if there are no components.
ActionsUpdates all the selected entries. The options are:
  • Batch Update: Updates all the selected entries when Update (button) is clicked and the change is confirmed.
    • Group: Changes the name of the group to the one entered in the adjacent block.
    • % Complete: Sets the percentage complete to the number entered in the adjacent block (e.g. 25 for 25% complete).
    • % Invoiced: Sets the percentage invoiced to the number entered in the adjacent block (e.g. 25 for 25% complete).
  • Set % Invoice = % Complete: Sets the percentage invoiced to match the percentage complete.
  • Order by Group > Description: Arranges the entries by group and then by description.
  • Delete: Deletes the entry.
EditLets you edit the components.

Fields Explained

Info

Fields marked in blue (✎) can be edited.

Field Description
Field Chooser (*)Add or remove columns.
IDThe system-generated number for the component entry.
FromThe source transaction
Order IDThe system-generated number that indicates the order of the entry.
DescriptionThe component's description (e.g. Wardrobe, Bar Cabinets, Kitchen Units).
GroupThe name of the group that the component is in (e.g. Floor 1, Floor 2)
Total (exc)The total VAT exclusive amount charged for the component.
% CompleteThe percentage of the component that is completed.
% InvoicedThe percentage of the component invoiced.
% VarThe percentage difference between the completed and invoiced amount.
Total (Var)The amount difference between the completed and invoiced amount.
Menu (...)A submenu with the following options:
  • Move Up: Moves the entry one line higher.
  • Move Down: Moves the entry one line lower.
  • Delete: Deletes the entry.

Gantt (tab)

  • Displays a list of tasks and marks off the days on the calendar.
  • The Gantt diagram only displays the levels that are affected by scheduling.

Data Pipelines for Output

The Data Pipelines for Service Manager Output Templates are listed in Output Data Pipelines.

Report an issue with this page

For more useful feedback, select the text on the page you're reporting about, then click Feedback again — or continue without selecting anything.